Project Description Type / Scope of Work Client / Contractor Consultant
Jumeirah Beach Residence Project (JBR 3) Piling Works Tecom / Mace: Mace / Arenco
(5B+G+34) Wind Tower 1, plot No.B3 JLT, Dubai Shoring Works Dr.R.M. Azizi / The Wind FZ LLC Farayand Arch. & Engg.
(3B+P+G+35+Mech.Room) Tower, Plot No.Q1,JLT,Dubai Piling & Shoring Works Saba R.E Al-Hawraa
(4B+G+34) Comm. Res. Tower Plot No.E1 @ JLT Shoring & Piling Works Best Homes W.S Atkins
Arshia Marina Tower, Proposed 2B+G+30 & 2B+G+1 Com.Res.Bldg. Plot No.392-455 (5N) Marsa, Dubai. Piling & Shoring Works Arshia Marina Co. Al-Hawraa Consultant
Gate Garden District-Package No.G20000 For DIFC Piling & Shoring Works DIFC / MACE (Client Representative) Hopkins Consultant
(3B+G+44+R) Res. Tower, Plot No.j2 at JLT, Dubai Piling & Shoring Works Mr.Moh’d Abdullah Bin Obaidullah Art Consultant
Proposed 5B+G+39 Storey Offices & Furnished Appartment Tower on Plot No.C2 at JLT, Dubai Shoring Works Ascon M/s.Dar Consultant
LakeShore Tower 1 (JLT) Plot No.JLT-PH2-Y2 for Al Bodor Real Estate Development Piling Works Capital Investment M/s.Khatib & Alami
(3B+G+12) Bldg. for Mr.Salem Abdulla Bin Touq on Plot No. 241-458 Al Nahda Shoring Works OST Construction M/s.Ziki Homsi
(3B+G+12) Office Bldg. on Plot – T2 JLT Dubai Piling and Shoring Works Han Investments National Engineering Bureau
(B+G+M+41 FLRS) Res./Comm. Bldg. Plot No.335-147 at Trade Center First, for H.E.Al.Sheikh Rashid Bin Khalifa Bin Saeed Al Maktoum Piling & Shoring Works Al Shafar Contr. Incorporated (Conin)
(4B+G+6P+1HC+27) Typ.Floor Comm./Office Tower on Plot No. BB.A02.017 at Buiness Bay, Duabi Piling & Shoring Works M/s. ETA Star Property Developers M/s. N.E.B
(G+55) Storey Tower & (G+8) Car Parking Building Plot No. 336-208 (Maze Tower), Trade Center Second, Dubai Earth Works & Piling Works Mr.Abdulla Hassan Al Rostamani M/s. Dar Consultant
Proposed (G+M+69) H.H.H.R Tower for H.H.Sheikh Hamadan Bin Rashid Al Maktoum on Plot No 335-112,335-203 at Trade Center First, Sheikh Zayed Road Piling & Shoring Works H.H. Sheikh Hamadan Bin Rashid Al Maktoum M/s. Al Hashemi
Hilton Hotel & Resorts – Ras Al Khaimah Piling Works Govt. of Ras Al-Khaima-Ruler’s Court M/s. W.S Atkins
MOTOR CITY – Automall complex at Nad Al Shibba Piling & Shoring Works M/s.Union Properties M/s.EDARA / N.E.B
R 659/11 – Comprehensive Improvement of Sheikh Zayed Road, Jumeira Lake Towers INterchange (I/C 5.5) Piling Works M/s.Dutco Balfour Beatty / M/s. Road Transport Authority M/s. Parsons De Leuw Cather
5B+G+2M+27 Corp.Executive Hotel & Offices on Plot No.BB.A01.036 at Business Bay – Duabi Shoring (Contiguous & Piling Works) M/s.Reef Real Estate & H.H Sheikh Mohammad Zayed Saqer Al Nahyan M/s.Erga Progress
R882/2- Improvement of Al Safooh Area Road Network Roads R3 & R5 Piling Works M/s. Wade Adams Cont./M/s. RTA M/s.Parsons De Leuw Cather
Lam Tara Towers Podium (6B+G+M+10P) + Res.Tower (6Mech+70 Flrs) + Office Tower (5Mech+60 Flrs) on Plot No.343-983 at Al Wasl, Sheikh Zayed Road, Dubai. Piling & Shoring Works Mr.Saeed Manana Ghedair Ejtebi M/s.Dimensions Engg.Consultants/M/s.Al Binaa Project Manager
Dubai World Central International Airport Project No.JXBI/BLD/420 – Air Traffic Control Tower Piling Works M/s.Government of Dubai, Department of Civil Aviation / M/s.Arabtec Construction L.L.C M/s.Dar Al-Handasah Shair & Partners
La Hoya Bay Reidence -1 at Al Marjan Island at Ras Al Khaimah – Package 0515 Piling Works M/s.Khoie Properties M/s.Al Turath Engg.Consultants
Reef Ajman Tower at Nakheel (B), Block O, Ajman Shoring Works (Contiguous) M/s. Reef Real Estate M/s. Keo International
(2B+G+12FL+R)Bldg. on Plot No.241-399 at Al Nahda 2nd Dubai – U.A.E Shoring Works (U-Beams + Secant) M/s.Hana & Maryam Banat Obaid Mohammad Abdulla Al Helo M/s.Art Consultant
(3B+G+MC+45F+R) Tower on Plot No.JLT-PH1-M2 at Jumeirah Lake Towers, Dubai. Shoring Works (Contiguous Pile) Mr. Mohammad Ibrahim Obaidullah M/s. Art Consultants
Clayton Residency on Plot no BB.B03.004 at Business Bay, Dubaii Piling and Shoring Works (U-beams) M/s. Deyaar Development PSC M/s. Arab Experts Engineering Consultants (AREX)
Fortune Avenue Tower on Plot no. BB.A06.018 at Business Bay, Dubai Piling & Shoring (Secant Pile) M/s. Fortune Investment Group L.L.C. M/s. Architecture & Engineering Innovations Bureau
The Courts Tower on Plot no. BB.A02.015 at Business Bay, Dubai Piling & Shoring (Diaphragm wall) M/s. Tanmiyat Group M/s. Mansouri & Bayaty Architects (M.B.A)
Jaddaf Project on Plot no A03, A04, E13, D10, D12 & D13 Shoring Works (Secant) M/s. RGM Limited / Ms.CPM M/s.ARENCO
Contract R881/2C Comprehensive Improvement of the Parallel Roads, Dubai Piling Works M/s. Roads & Transport Authority (RTA) / M/s. Salini Dubai M/s. Parsons De Leuw Cather
Marina Arcade on Plot no. 392-489 at Dubai Marina, Dubai Piling & Shoring Works (Secant) M/s. Mada’in Properties / M/s. international Project Management (IPM) M/s. Arc International
Palm Jumeirah Sofitel Resort at Palm Jumeirah, Crescent Parcel no. PJCR 28 & PJCR 29, Dubai Piling Works M/s. Mirk General Trading L.L.c. M/s. Burt Hill
(4B+G+3P+24Sorey) Residential and Retail Building on Plot no. P1.D011 at Culture Village, Dubai Shoring Works (Secant Piles) M/s. Emirates Sunlad Group M/s. Al Wasl Al Jadeed Consultants/ Design Concepts
Residential Tower (2B+G+3Podiums + Recreation + 18 Floors) on Plot no. BB.B03.005 at Business Bay, Dubai for M/s. Farida Farnood Shoring (Secant Pile) and Piling M/s. Farida Farnood/ M/s. Sherkhan Farnood General Trading Co. Arab Experts Engg. Consultants
Commercial Building for Mr. Ahmed Mubarak Al Mazrouri on Plot no. C-86, Sector E-11, Abu Dhabi Shoring (Secant Pile) and Piling Works M/s. Al Fara’a General Contracting M/s. Al Turath Engineering
4B+G+45FLOORS Building in Kabul, Afghanistan Piling Works M/s. Azizi Investment
Construction of Batinah Costal Road Phase – 1, Section 11 from Km 176+000 to Km 241+67, Sultanate of Oman Piling Works Supreme Committee for Town Planning, Sultanate of Oman./ Nagarjuna Construction Company International LLC.. National Engineering Services
STELLA Dubai Hotel 3B+G+30 Floors on Plot No.(392-436), Marsa Dubai, Dubai for M/s. Ayoub Adly Ayoub Ghattas Shoring Works (Secant piling + U Beams) & Demolition Works M/s. Ayoub Adly Ayoub Ghattas M/S CONIN (Incorporated Consultants)
Commercial Building for Mr.Hadi Hamad Hwaired Al Mansouri Plot No.C-9, Sector M2-12, Abu Dhabi. Shoring & Piling Works M/s.Al Qantara General Contracting Company M/s.American Consultant Office.
(2B+G+35) (2B+G+30) AL FATTAN Mix use on Plot No. 392-513 @ Marsa Dubai Shoring & Piling Works AL FATTAN Properties M/S IMAGE
(2B+G+19) Harbour Residence on Plot No. 392-484, Marsa Dubai for Marina 3K Limited Shoring & Piling Works (Secant) MARINA 3K LIMITED – EMAAR BARAJEEL CONSULTANT/AL HAWRA’A ENGINEERING
Proposed (B+G+31) Hotel Building on Plot No. 392-426 @ Marsa, Dubai SHORING (BEAMS) & PILING WORKS NEW DUBAI PROPERTY AL AJMI ENGINEERING CONSULTANTS
R1013 Hotel Building 2B+G+M+7+HC on Plot No. 124-170, Al Muraqabat, Dubai ENabling works WASL (Asset Management Group) Dimensions Architecture Unlimited
Al Jaziri Tower (3B+G+3P+60 Floor) On Plot No. BB.AA03.023 & 024 at Business Bay, Dubai Shoring Works (Secant Wall) M/S KELE CONTRACTING M/S NED
P30-Proposed B+G+M+7 Typical Mixed Development and G+4+R multi-Storey Building, DAFZA, Dubai Shoring (Beams) & Piling Works M/S DAFZA M/S LACASA Architects & Engineering Consultants
Dubai Creek Harbour Project @ Lagoon, Dubai Piling Works M/S EMAAR M/S W.S ATKINS
FOUNTAIN VIEW No.1,2 & 3 Piling Works EMAAR DEWAN AL AMARA
Dubai Mall Expansion (Zone 1,2 & 3) Shoring & Piling Works EMAAR M/S WSP/TURNER
Proposed (4B+G+14) National Bank of Abu Dhabi Building On Plot NO. 326-1451 @ Al Jaddaf, Dubai-UAE Piling & Shoring Works (Diaphragm Wall) M/S AL AMAR ENGINEERING & CONTRACTING CO.LLC M/S ARENCO
PROPOSED HOTEL 1 THE AVENUE PHASE2 @ AL WASL, DUBAI-UAE Piling Works M/S MERRAS HOLDING M/S WME
PROPOSED MIXED USE DEVELOPMENT AL FATTAN TOWERS ON PLOTNO. 215-0458 @ UMM RAMOOL, DUBAI-UAE Shorinng (Beams) + Piling Works M/S AL FATTAN PROPERTIES M/S AE7
AFC 023 Serviced Apts. @ Al Furjan, Dubai Shorinng (Contiguous) + Beams + Piling Shk Ahmed Bin Mohd Bin Zayed Bin Saar M/S Global Engineering Office
Double Tree by Hilton Hotel @ Masdar City, Abu Dhabi Shoring (Contiguous) + Piling Work Reliable Property Invest. M/S Global Engineering Office
DDubai Inn Hotel @ AL WASL Shoring & Piling Works M/S. EMAAR PROPERTIES PJSC. M/S. ARCH GROUP CONSULTANTS
DDubai Inn Hotel @ Marina Shoring & Piling Works M/S. EMAAR PROPERTIES PJSC. M/S. ARCH GROUP CONSULTANTS
Fountain Substation at Downtown Dubai Development M/S. TURNER/EEE M/S. POYRY ENERGY
Bateen Marina Resort Development Plot No. C103, Sector W-35 – Abu Dhabi Secant + Diaphragm+Piling H.H.SHK MOHD BIN KHALIFA M/S. ACG
W – Resort Hotel & Residence @ Palm Jumeirah Drilling of Deepwells M/S. ACTION INTERNATIONAL DRILING SERVICES & DEWATERING LLC M/S. RMJM
W – Resort Hotel & Residence @ Palm Jumeirah Contiguous + Piling Works M/S. AZIZI INVESTMENT LLC M/S. GAJ / M/S. SHEPHERD GILMOUR
Entisar Tower @ Shaikh Zayed Road, Dubai – UAE Trial Pits M/S. MEYDAN GROUP LLC M/S. AE7
W – Resort Hotel & Residence @ Palm Jumeirah Shoring – Beams M/S. AL FUTTAIM CARILLION M/S. RMJM
Proposed Nikki Beach Resort For M/s. DSA Architects International @ Pearl Jumeirah – Dubai Shoring (U-Beams) M/S. BROOKFIELD MULTIPLEX M/S. D. S. A
(B+G+7+Roof) Residential / Hotel Apts. On Plot No. PJCRC14 @ Palm Jumeirah Piling Works M/S. C FOURTEEN FZE / GCC M/S. NATIONAL ENGINEERING BUREAU
(B+G+8+GYM) Hotel Project on Plot No. PJCRC38F @ Palm Jumeirah Enabling Works (Shoring + Piling) M/S. NEW DUBAI PROPERTIES M/S. RIMAL ENG. CONSULTANTS
(G+8TYP.+Roof) Residential Building On Plot No. 22-026 @ Dubai Silicon Oasis Shoring Beam M/S. ANC CONTRACTING DUBAI
Al Fattan Down Town On Plot No. 3340109 @ Al Wasl – Dubai Shoring (Secant Pile) + Piling Works M/S. AL FATTAN M/S. AE7
(G+8+GYM) On Plot No. 21-017 Axis – Gold 5 @ Silicon Oasis Shoring Beam M/S. ANC CONTRACTING DUBAI M/S. DESIGN CENTER
Site Preparation Fencing, Offices On Plot No. 275 (681-1107) Al Barsha, South Fourth (681), JVC Dubai, U.A.E. Site Preparation (Fencing, Offices & Sign Board) FAST LINK / MR. ALI MOHD. SALEM ABU ADAS M/S. AL GURG CONSULTANT
Five Story Labour Accommodation Building for M/s. BILT MIDDLE EAST LLC on Plot No.559-1773 at Jebel Ali Industurial (1), Dubai, UAE Shoring (U-Beams) M/S. BILT MIDDLE EAST LLC / M/S. AL BASTI & MUKTHA LLC M/S. AL SARAYA ENGINEERING CONSULTANTS
W – Resort Hotel & Residence @ Palm Jumeirah – On Plot No. PJCRC09 & C10 Sheet Piling M/S. ACTION M/S. RMJM
(B+G+4FLRS.+R) Bldg. On Plot No. JVC 13C MRA 007 @ Al Barsha South Fourth – Dubai Shoring (U-Beams) JAMAL HAMAD AL SAGHEER M/S. DIMENSIONS
Resort Hotel Building (B+G+13) for Mr. Abdullah Ahmad Al Moosa On Plot No. PJTRH02 @ Palm Jumeirah Piling Works M/S. CHINA STATE / M/S. BAUER M/S. ARENCO
For Proposed Ladybird Early Learning Center for M/s. Malicon Holldings Ltd. On Plot No. JVC12NUP001, Jumeirah Village Circle, Dubai – U.A.E. Shoring (U-Beams) M/S. AL SHAFAR CONTRACTING CO. LLC M/S. SHEPHERD GLIMOUR
Hotel Building (2B+G+2P+18+Roof) On Plot No. BB.A05.008 @ Business Bay Shoring (beams + secant) + Piling M/S. NEW DUBAI PROPERTIES M/S. RIMAL ENG. CONSULTANTS
Hotel (B+G+22) On Plot No. 143 (392-454) @ Dubai Marina – The One Hotel Shoring (beams) + Piling M/S. NEW DUBAI PROPERTIES M/S. AL AJMI ENG. CONSULTANTS
Proposed (B+G+2) Spring Community Center On Plot No. 394-6998 @ Emirates Hills – Dubai Shoring (Secant + Contiguous) + Piling Works M/S. EMAAR PROPERTIES PJSC M/S. DAR CONSULTANTS
Proposed (B+G+4+Roof) Residential Building for M/s. Emad Aziz Mitry Saad On Plot No. JVC14CMRP004 @ Jumeirah Village – Dubai Shoring (U-Beams) M/S. AL SAYEGH CONTRACTING LLC M/S. WINNERS CONSULTANT ENGINEERING
(B+G+4) Residential Building On Plot No. JVC13KMRP003 @ Al Barsha South Fourth, Dubai Shoring (Beams + Contiguous) MOH’D AL BARGUTHI & ALI MOH’D ABU ADAS / M/S. FAST LINK REAL ESTATE M/S. AL GURG CONSULTANTS
Proposed (2B+G+5) Ports View Mixed Use Development On Plot No. 321-2722, Dubai – U.A.E. Shoring Works (Contiguous) M/S. AL WASL M/S. ARKITEKNIK INTERNATIONAL
(B+G+7+R) Residential Building On Plot No. IC3-C-29-34 at Al Warsan Fourth 624, International City – Dubai Shoring ( U-Beams) M/S. AL ASHRAM CONTRACTING LLC M/S. ERGA PROGRESS
Fountain Views Exit Tunnel to M003 Road (FV Mini Tunnel) Shoring Works M/S. EMAAR PROPERTIES PJSC. / M/S. TURNER M/S. HALCROW
(3B+G+2P+19) SOL Avenue Tower Plot No. 346-647 at Business Bay Reanchoring Works M/S. BHATIA CONTRACTING
Construction of Hotel Apartment On Plot No. PJCRC 35A-B @ Palm Jumeirah, Dubai Secant Wall M/S. FAST LINE INVEST / ALI MOH’D ABU ADAS M/S. NORR GROUP
Mulberry @ Park Heights Phase 1, Dubai Piling Works M/S. EMAAR PROPERTIES PJSC. M/S. FAITH FULL & GOULD / M/S. LACASA
Proposed 3B+G+M+30 Hotel Building On Plot No. C-008-013, TECOM -Dubai, U.A.E. Secant Wall + Piling ABDUL RAHMAN ABDULLA MOHD AL JAZIRI / BADER ABDULLA MOHD AL JAZIRI M/S. DESIGN CENTER
Proposed (B+G+1) Villas On Plot No. PJJPFJ37 FROND J & Plot No. PJJPF106 & 107 FROND I @ Palm Jumeirah, Dubai Shoring U-Beams M/S. MOHAMMED JAWDAT AYESH MUSTAFA AL BARGUTHI & M/S. FAST LINE M/S. WHITE SPACE ARCHITECTS
Down Town Dubai Development Fountain Views Residential Entrance Tunnel Shoring Works M/S. EMAAR PROPERTIES PJSC. M/S. HALCROW
(2B+G+14+Health Club) & (2B+G+12+Health Club) Comm. & Residnetial Bldg. On Plot No. 326-1667 @ Jaddaf, Dubai Shoring (Contiguous Piles) M/S. FGB / MISMAK M/S. NATIONAL ENGINEERING BUREAU
Proposed Commercial & Resd. Building (G+7) On Plot No.: (317-222) @ Al Mankhool, Dubai – UAE Shoring Works (Beams + Secant) MR. ADIL KAMIL HASIM BARQAN MUSTAFAWI M/S. ART CONSULTANTS
G+3P+13 Typical Residential + 2H Residential Building On Plot No. 275 (681-1107) @ Al Barsha South (681) JVC, Dubai – U.A.E Piling Works MR. ALI MOH’D SALEM ABU ADAS / M/S.FAST LINE REAL ESTATE DEVELOPMENT M/S. AL GURG CONSULTANTS
Dubai Parks Lagoon Phase 1 Piling Works M/S. AL NASR CONTRACTING CO. LLC M/S. CHSS
Proposed Hotel (3B+G+6F) On Plot No. 326-0897 @ Jaddaf for Mr. Hashim Abdulla Ahmad Al Dabal Secant + Piling Works MR. HASHIM ABDULLA AHMAD AL DABAL M/S. ERGA PROGRESS
Adventz Tower On Plot No.345-391, Burj Khalifa District, Dubai-UAE Shoring (Secant) M/S. SJM ELYSIUM PROPERTIES LLC / SYNERGY PROPERTY DEVELOPMENT M/S. AL BURJ CONSULTANTS
Mixed Use Development on Plot 8884532 (Plot – 03) Deira Waterfront Development, Dubai – UAE Shoring (Secant) + Piling Works M/S.DEIRA WATERFRONT DEVELOPMENT M/S.AE7
Mixed Use Development on Plot 8884426 (Plot – 13) Deira Waterfront Development, Dubai – UAE Shoring (Secant + Diaphragm)n + Piling Works M/S.DEIRA WATERFRONT DEVELOPMENT M/S. AE7
R0477 Res. Bldg. On Plot No. 359-0973 @ Al Quoz, Dubai – UAE Preliminary Works + Excavation M/S. AL WASL M/S. AL GURG CONSULTANTS
R1065 Hotel Staff Accommodation On Plot No. 359-0963 @ Al Quoz, Dubai – UAE Shoring (U-Beams) M/S. AL WASL M/S. ARKIPLAN CONSULTING ARCHITECTS & ENGINEERS
(B+G+8+GYM) Hotel Building On Plot No. PJCRC32G @ Palm Jumeirah Dubai – UAE Shoring & Piling Work M/S. REEM AL SHARAI GENERAL TRADING L.L.C / M/S. NEW DUBAI PROPERTIES M/S. RIMAL ENG. CONSULTANTS
Proposed (B+G+1P+16+R) Hotel Building On Plot No. 346-585 @ Business Bay, Dubai – UAE Shoring (U-Beams) + Piling AL SAHIL AL AKHDER / M/S. NEW DUBAI PROPERTIES M/S. AL AJMI ENG. CONSULTANTS
Meydan Beach Hotel for Enabling Works – Package II – Shoring & Excavation Works
Shoring Works (Secant Piles) M/S. MEYDAN GROUP LLC M/S. AE7 Dubai Mall Zaabel Expansion
Shoring (U-Beams) M/S. BROOKFIELD MULTIPLEX M/S. AECOM DPDP-6009 – Infrastructure Work Phase Dubai Parks, Hotel – 1 Bridge
PILING WORKS M/S. GHANTOOT CONTRACTING M/S. HALCROW Comprehensive Improvements Of The Parallel Roads-Phase 2A
DRILLING FOR DEEP WELL M/S. ACTION
Town Square – Proposed Resid. & Comm. Mix Developments On Plots No. 922-8918 (PH-01-009 & 010) Al Yalayes – Dubai, UAE Piling Works + Shoring(U-Beams) M/S. NSHMI DEVELOPMENT LLC M/S. AL GURG CONSULTANTS
Emaar Properties PJSC Proposed Pedestrian Bridge Address Connection Burj Khalifa Development Dubai – UAE Piling Works M/S. DUTCO / M/S. EMAAR PROPERTIES PJSC M/S. AECOM
Improvement of Al Wasl road Phase 1B Interchange 2.5 – R921/1B Piling Works M/S. CHINA STATE / RTA M/S. PARSONS
The Lagoons-Phase 1 Proposed DCH Sales Center Bldg. (G+2) @ Al Kheeran, Dubai – U.A.E. Excavation & backfilling Works M/S. EMAAR PROPERTIES PJSC M/S. TURNER
Address Residences – Dubai Opera @ Dubai Downtown, Plot – A2 & A3 Shoring Works by Diaphragm Wall M/S. EMAAR PROPERTIES PJSC M/S. KHATIB & ALAMI
Dubai Mall Expansion (ZABEL AREA) Additional Load Tests M/.S. HEGAZY / M/S. EMAAR PROPERTIES PJSC M/S. HEGAZY
Zabeel Feed Mill On Plot No.: 841-3156, Margham, Dubai, U.A.E. (FNC Project Ref. No. # 6345) Piling Works M/S. FUJAIRAH NATIONAL CONSTRICTION CO. L.L.C M/S. AE7
HIRING EQUIPMENTS Hiring Equipments DIC
Arabian Crown Tower Plot No. 045-07 A, City of Arabia, Dubai. Piling Works M/S. MIDDLE EAST DEVELOPMENT M/S. OPTIMUM ENGINEERING
G + 7 Typical Floors + Roof On Plot No. AC4-42 at Dubai World Central – Dubai, U.A.E. Shoring U-Beams M/S. RADAR DWC LLC / MS. AL JAWAL CONTRACTING COMPANY M/S. NATIONAL ENGINEERING BUREAU
Retail Mall Car Park @ Dubai Hills Estate – Dubai, U.A.E. Piling Works M/S. EMAAR PROPERTIES PJSC. M/S. ARCADIS
Proposed (2B+G+55F) Meydan Beach Hotel Enabling Package II Piling Works On Plot No.392 0549 @ Marsa, Dubai , UAE Piling Works M/S. MEYDAN GROUP LLC M/S. AE7
Town Square Development Proposed (G+1P+11+HC FLR) Residential Bldg. On Plot No. 035, Al Qudra, Dubai Piling Works M/S. NSHMI DEVELOPMENT LLC / M/S. KIER M/S. MIMAR EMIRATES ENGINEERING CONSULTANTS
Retail Mall Car Park – Foundation for Tower Crane @ Dubai Hills Estate – Dubai, U.A.E. Piling Works M/S. ALEC M/S. ARCADIS
Proposed B+G+6+ROOF Building for Mr. Hussam Anawar Iskandar Rabadi On Plot No. 326-0938 at Culture Village, Al Jadaf, Dubai – U.A.E. Shoring Works M/S. AL JAWAL CONTRACTING M/S. EMIRATES ENGINEER CONSULTANT
4B+G+51 Mix Use Development & 4B+G+9 Parking Building On Plot No. 335-143/184, Dubai – U.A.E. Shoring + Piling Works H.E MOHAMED KHALIFA BIN YOUSEF ALSUWAIDI M/S. ARKITEKNIK INTERNATIONAL
Dubai Creek Harbor Development – Vida Hotel, Enabling Works Piling Works M/S. EMAAR PROPERTIES PJSC. M/S. MRIAGE / M/S. GAJ / M/S. ASG
Dubai Creek Harbor Development – Under Ground Car Park, Lagoon, Ras Al Khor, Dubai Piling Works M/S. EMAAR PROPERTIES PJSC. M/S. BH.N.S ENGINEERING CONSULATANT / M/S. FAITHFUL+GOULD LIMITED
Town Square Development – Proposed (B+G+P+(14,8,12,6)+R) Residential & Commercial Bldg. On Plot No. 922-8950 (PH-01, 032 & 033), Al Qudra – Dubai